Battery-storage costs must drop by 15 % year for India to avoid adding new coal capacity: Report

admin admin | 08-22 00:20

No new coal additions might be needed if the BESS costs, excluding the cost of finance, fall to around INR 60 lakh per megawatt-hour (MWh).
India might avoid building new coal plants and could limit its coal capacity to planned levels by 2032 if the cost of battery-storage systems drops by 15 % annually, according to a new report. Nearly 75 % of India's electricity is generated using coal. However, to meet its goal of reaching net-zero emissions by 2070, the country needs to reduce its dependence on coal and increase the use of renewable-energy sources like solar and wind power.

The challenge is that solar and wind power plants only generate electricity when the sun is shining or the wind is blowing. Therefore, energy-storage systems are needed to store this energy and use it during periods of low generation.

This is mainly because slow storage growth will hinder sustained renewable energy expansion once India's solar share in the power mix crosses 25 %. Currently, solar accounts for around 7 % of India's total power generation.

"And if BESS costs fall by 15 % on average each year, it would enable India to potentially limit its coal capacity to the 14th National Electricity Plan projection of 260 GW by 2032," the report reads.

It also notes that if the battery costs fall faster, the power sector could rely more on renewable energy, meeting 83 % of the electricity demand during the day by 2032. However, during non-solar hours, renewable energy might only cover 38 % of the demand due to the current storage limitations.

The report says building new coal capacity comes with risks and challenges. Coal capacity would need to ramp up and down more frequently, and if the BESS costs fall faster than anticipated, these new plants would face severe lock-in and underutilisation risks.

A K Saxena, senior director of electricity and renewables at the TERI, said: "Energy storage holds the key to the decarbonisation of electricity generation. A reduction in the cost of storage options would accelerate the energy transition in economies."

No new coal additions might be needed if the BESS costs, excluding the cost of finance, fall to around INR 60 lakh per megawatt-hour (MWh).

While recent declines in the BESS costs have been significant, the report says they need to drop by more than 50 % from the current levels to follow a least-cost pathway that avoids new coal capacity, especially for meeting non-solar demand.

Neshwin Rodrigues, electricity policy analyst at Ember, said: "Planners will now need to consider strategies for shifting solar generation to non-solar hours to ensure that the pace of the transition does not slow down. Therefore, while declining battery-storage costs are crucial, it is also important to focus on increasing the annual renewable-energy capacity, securing necessary financing and enhancing coal plant flexibility."

Nayeem Khan, a research associate at the TERI, said: "Accelerated growth in solar and wind, the development of pumped hydro projects and cost-competitive low-carbon technologies like BESS are essential for India to avoid new coal capacity."

Disclaimer: The copyright of this article belongs to the original author. Reposting this article is solely for the purpose of information dissemination and does not constitute any investment advice. If there is any infringement, please contact us immediately. We will make corrections or deletions as necessary. Thank you.


ALSO READ

Hyundai Motor India lists with record IPO, commits to Indian market with new tech and EV plans

As part of its effort to introduce clean mobility solutions for Indian buyers, Hyundai will launch f...

auto | 7 hours ago

Skoda Auto Volkswagen India plants over 7 lakh trees in Maharashtra for ecological restoration

Additionally, SAVWIPL has installed 18.5 MWp of rooftop solar power at its Chakan facility, which of...

auto | 7 hours ago

Mega Corporation launches Lendingo to enhance EV financing solutions

Mega Corporation on Monday announced the launch of a new division, Lendingo. Mega Corporation on Mon...

auto | 7 hours ago

GreenLine accelerates decarbonisation efforts with 1,000 LNG trucks by March 2025

The government in a recent draft policy proposed to convert a third of long-haul trucks into LNG pow...

auto | 7 hours ago

Remsons Industries acquires 51% stake in BEE Lighting to enhance automotive lighting solutions

Established in 2006, BEE Lighting specialises in automotive headlamps, rear lamps, and various exter...

auto | 7 hours ago

EV Recharge partners with ZEVO for mobile EV charging solutions

EV Recharge’s technology can charge vehicles from 0% to 80% in just 20 minutes, a significant improv...

auto | 7 hours ago